About that, that autumn is on the doorstep, resemble not only rains and yellow leaves, but also the thermometer, which relentlessly strive to the bottom. In spite of everything, bad weather and frosts will not take the plant staff by surprise, because preparations for winter were actually started here in April.
As part of preparing the enterprise for work in the cold season, measures were developed «Preparing the enterprise for work in the autumn-winter period 2012-2013 years», which are approved by order for the enterprise No. 21 dated 19.03.2012 The main burden for the implementation of the planned falls on the month of October..
Of the planned 1500 m2 roof repair (workshop buildings 01, 10) already finished – about 800 m2. At the moment, work is underway to repair the roof of the workshop building. 01. The glazing of windows and the insulation of the gates of the production units are made on 60 %.
To check the readiness and acceptance of production facilities at the enterprise, a special commission was created, headed by the chief engineer..